Construction Projects

SOUTH GA APRON REHABILITATION PROJECT

Aerial 2

Picture Plans Work Areas 2
PROJECT
Work consists of pavement rehabilitation of general aviation apron including pavement demolition and rubblization, hot mixed asphalt (HMA) paving, Portland cement concrete (PCC) paving, drainage rehab, hangar demo, sealcoating and pavement markings.

CONTRACTOR
Nelson Construction

ENGINEER
Mead & Hunt Engineering

PROJECT COST
Budget w/ contingency $14,253,486
Funding Sources:
     FAA AIP Entitlement & Discretionary Grant = $11,486,504
     FAA CARES Grant = 
$2,766,982

PROJECT SCHEDULE - updated 6/10/2022
Schedule Disclaimer: Dependent on weather & pre-conconstruction assumptions.

PICTURES(updated 6/10/22)

WORK AREAS
Work Areas 1 - 11 Overall Diagram
Work Areas 2 & 3 Diagram: These Work Areas occur within the Taxiway Safety Area which will require closures of the taxiway in these areas. Back-Taxis on the runway will be in effect.

IN PROGRESS!

CONSTRUCTION ZONE 2:
 Work Area #3 - (updated 7/12/22)    

     Commenced: Wednesday, June 29
     Anticipated Completion: Saturday, July 23

Twy A3 CLOSED
Twy A CLOSED from North end of Terminal Apron to approx. 810 ft. south of Twy A2.

South Hangar aircraft access via the Northwest opening of north t-hangar row.  
       
UPCOMING WORK!

Zone 3: Work Area #5-East, #7 and #8 (updated 7/12/22)  
     Schedule:  COMMENCING MONDAY, JULY 18
                        ANTICIPATED COMPLETION:  SEPTEMBER 1 
     
Electrical Update for Hangars  (updated 7/12/22)  
      Zone 3/W.A. #8 will include Pacific Power placing a new electrical pole on the north end of Hangar 118 along with placement of conduit and electrical service to a new transformer that will be located on the west side of Hangar 118. 

     In addition, the Port has expanded its original scope of work to include new electrical wiring and lighting in the (4) South T-hangar rows. Walla Walla Electric to run new wire through all the hangar rows to include the following:
     - (1) new LED light fixture and a single wall switch in each individual hangar space
     - Each hangar row will have 20-amp, 120-volt circuits for a GFCI outlet in each individual hangar space. 

     Week of July 18 - 23 concurrent construction in Zone 2 and Zone 3. (updated 7/12/22)  
          See diagram with effected work areas and access diagram.

     July 24 - September 1 construction in Zone 3. (updated 7/12/22)  
          See diagram with effected work areas and access diagram.   

Zone 4: Work Areas #4 and #5
     Schedule: ANTICIPATED COMMENCEMENT 8/29/2022      

Zone 5: Work Area 1
     Schedule: ANTICIPATED COMMENCEMENT 9/29/2022    

Zone 7: Work Area 2 (Taxiway Closure Effects)
     Schedule: ANTICIPATED COMMENCEMENT 10/28/2022    

HANGAR ACCESS
Construction in Work Areas 6, 7, and 10 will have no ingress/egress for an aircraft into the South T-Hangars as the concrete will be completely removed and replaced.

TEMPORARY AIRCRAFT ACCOMMODATIONS
     Tie-Downs: See diagram for TEMPORARY TIE-DOWN OPTIONS
     Gorge Aviation FBO: call 509-540-1081

 GA TENANT MEETING (from February 15)