Construction Projects

SOUTH GA APRON REHABILITATION PROJECT

Aerial 2

Picture Plans Work Areas 2
PROJECT
Work consists of pavement rehabilitation of general aviation apron including pavement demolition and rubblization, hot mixed asphalt (HMA) paving, Portland cement concrete (PCC) paving, drainage rehab, hangar demo, sealcoating and pavement markings.

CONTRACTOR
Nelson Construction

ENGINEER
Mead & Hunt Engineering

PROJECT COST
Budget w/ contingency $14,253,486
Funding Sources:
     FAA AIP Entitlement & Discretionary Grant = $11,486,504
     FAA CARES Grant = 
$2,766,982

PROJECT SCHEDULE - updated 6/10/2022
Schedule Disclaimer: Dependent on weather & pre-conconstruction assumptions.

PICTURES(updated 6/10/22)

WORK AREAS
Work Areas 1 - 11 Overall Diagram
Work Areas 2 & 3 Diagram: These Work Areas occur within the Taxiway Safety Area which will require closures of the taxiway in these areas. Back-Taxis on the runway will be in effect.

IN PROGRESS!

CONSTRUCTION ZONE 1:
 Work Areas #6, #9 and #10 

     Work Areas #6 & #10: AIRCRAFT/VEHICLE ACCESS ALLOWED FOR W.A. #6 & #10! CONTRACTOR CONTINUING JOINT SEALING, TIE-DOWN INSTALL, MARKINGS AND CLEANING! 6/30/22 (updated 6/17/22)
           
     Work Area #9: ANTICIPATED COMPLETION 7/1/22 (updated 6/17/22)        
     

UPCOMING WORK!
Zone 2: Work Area #3 (Taxiway Closure Effects)

     Schedule:  COMMENCING WEDNESDAY, JUNE 29
                       ANTICIPATED COMPLETION:  SATURDAY, JULY 16
     Taxiway Closures: Twy A2 AND Twy A (North of Terminal apron to approx. 810' S. of Twy A2.

Zone 3: Work Areas #5 (East of Service Road), #7 & #8
     Schedule: ANTICIPATED COMMENCEMENT 7/25/2022 
          (Zone 6: Work Area #11 to be completed concurrently during Zone 3 work.)

Zone 4: Work Areas #4 and #5
     Schedule: ANTICIPATED COMMENCEMENT 8/29/2022      

Zone 5: Work Area 1
     Schedule: ANTICIPATED COMMENCEMENT 9/29/2022    

Zone 7: Work Area 2 (Taxiway Closure Effects)
     Schedule: ANTICIPATED COMMENCEMENT 10/28/2022    

HANGAR ACCESS
Construction in Work Areas 6, 7, and 10 will have no ingress/egress for an aircraft into the South T-Hangars as the concrete will be completely removed and replaced.

TEMPORARY AIRCRAFT ACCOMMODATIONS
     Tie-Downs: See diagram for TEMPORARY TIE-DOWN OPTIONS
     Gorge Aviation FBO: call 509-540-1081

 GA TENANT MEETING (from February 15)